8th Street Bridges Project page
Project Questions: 360-417-4800
Email:
    
Return to Home Page City Hall lobby hours are 8am until 5pm - Monday through Friday. Services Find it fast!

8th Street Bridges Replacement Project

The $18.4 million 8th Street Bridges Replacement Project consisted of removing the previous timber bridges and replacing them with 758 foot long reinforced concrete structures. The new bridges are 34 feet wide, curb to curb with 12-foot wide vehicle lanes, 5-foot bike shoulders, and 6.5 foot wide sidewalks on each side. The project also included extensive stormwater systems for stream protection and wetland restoration. Each bridge features two lookout areas with views of the Olympic Mountains and the Strait of Juan de Fuca.

The contractor for the project was Parsons RCI, Inc. of Sumner Washington with project management services provided by Exeltech Consulting, Inc.

The City greatly appreciates the cooperation and patience of the public during the construction of this major project and eagerly joins with the community in the celebration of opening both 8th Street Bridges.

The 8th Street Bridges Replacement Project Completed February 2009!
Thank you Port Angeles for your cooperation and patience!

February 24, 2009 - Both bridges opened to pedestrians only on the morning of February 24, from approximately 9:00 a.m. until 2:00 p.m. At 2:00 p.m., a brief opening and ribbon cutting ceremony was held just west of the intersection of 8th & Cherry on the east end of the Valley Creek Bridge.

Work continues on the deck of the Valley Creek Bridge Bridges are Open!

Immediately following the ceremony, vehicle traffic was escorted by Police and Fire Department vehicles from the 8th & Cherry intersection across the Valley Creek Bridge, continued west on 8th Street, and then across the Tumwater Valley Bridge. Both bridges were then open to east-bound and west-bound vehicle traffic.

  Getting Read
Glenn Cutler leads ceremony
 
Mayor Braun offers comments
Santosh from Exeltech
 
Greg Bennett from Parsons
Banner
 
Jim Mahlum & Glenn CutlerDeputy Mayor Wharton rides first offical bike acrossApproaching Tumwater Bridge
Procession



PROJECT HIGHLIGHTS


VALLEY CREEK BRIDGE GIRDER HAUL-IN
FINAL GIRDER HAUL-IN / June 2008

Tumwater Creek Bridge under construction"Return of the Gird-I" is the theme for the delivery of the girders for the Valley Creek Bridge. This marks another major milestone in the 8th Street Bridges Replacement Project. Girders for the Tumwater Bridge were delivered in April.

Beginning June 12 through June 19, 2008, twenty-five concrete girders for the Valley Creek Bridge were delivered and set into place. This marks another major milestone in the 8th Street Bridges Replacement Project.

The girders were manufactured by Concrete Technology Corporation and will be transported from Tacoma with special heavy-capacity trucks via Van Dyke, Inc.

Transportation of the girders required coordination with several agencies along the route and special permitting by the Washington State Department of Transportation.

Each one of the reinforced concrete girders weigh approximately 170,000 pounds, range in length from 138 to 155 feet and are 7 feet tall. The haul-in and setting process will require various street closures and delays at several intersections along the delivery routes.

Girder Truck arrives


Return of the Gird-IThe last five concrete girders for the Valley Creek Bridge were delivered and set into place by 11:30 a.m. on Thursday, June 19. This marks another major milestone in the 8th Street Bridges Replacement Project.

Thank you for your patience as we completed a major milestone in this project.

Click photo to view larger image size.

On June 19, beginning at approximately 7:00 a.m. five girders designated for the 8th & Cherry Street staging entered on Front Street, turned south on Race, proceeded up to 8th Street, and turned west onto to 8th and then continued down 8th Street to the construction area at bridge level. Traffic delays were very brief.

Making the corner at 8th & Race Streets
Staging near 8th & Cherry
Two girder trucks on 8th Street waiting to be unloaded
Backing in.  Crane is lifting one end of the girder while the other end remains on the jeep.  Jeep is pushed back into position.
Lifting girder up
Destination
Girder lifted by 2 cranes
Lifted over into position
Almost there
Wide view
   



June 16 and 18
- Five girders were delivered each day to be lifted into position at the Valley Creek site.
All girder trucks arrived at the site by 8:30 a.m. The final girder for June 18 was in place by 1:00 p.m.

First Girder goes into place on Wednesday.5th and last girder goes into place on June 18


June 13, 2008 - Five more girders arrived for the Valley Creek Bridge. Girder trucks arrived at approximately 7:30 a.m. and were all at the construction site by 8:45 a.m. This time the trucks delivered the girders under the bridge so they could be lifted up into position. Click photos to view larger image size.

Trucks arrive from Marine Drive
Trucks wait on Valley Street
Column waiting for a girder
Columns that will support these girders
Truck backs into position
Girder up
And up
Almost there
   

June 12, 2008 - The first set of 5 girders arrived for the Valley Creek Bridge. The first girder was in place by 9:15 a.m. Click on the photos below to view larger image sizes.

Girder trucks on 8th street
First end of the girder is lifted up by the first crane
Moving girder out over bridge
Over into position
Over a bit more
Easy does it down
Pushing into exact position
Girder finds it place

 


TUMWATER CREEK BRIDGE MAJOR MILESTONE
Girder Haul-In and Street Closures / April 1 - 9, 2008

Girder Haul-In / April 1, 2008
First Girder Truck arrives in Port Angeles - April 1, 2008 / No Foolin

Girder Truck arrives

Click photos to view larger image size

Goint Up Cedar
Backing In
Heading Up Cedar
Backed into position on 8th

Photo Montage
Click image below to view photo montage.
Note: You must have Adobe Acrobat reader installed to view this file. Click to get Adobe Reader download

Girder Haul-In / April 1 / No Foolin

Each one of the reinforced concrete girders weigh approximately 170,000 pounds, range in length from 138 to 155 feet and are 7 feet tall. The haul-in and setting process required an 8-day closure of the Tumwater Truck Route SR117, a one-day closure of Cedar Street and periodic closures of Marine Drive between and including the intersections of the Tumwater Street and Cedar Street.


April 3, 2008 Girder Haul-In
Photos of trucks arriving and traveling through Port Angeles to the construction site.
Click photos to view larger image size.

Entering Port Angeles near Mt. Pleasant Road
Turning south onto Truck Route
Heading east on Lauridsen to go back down the Truck Route
Girders Go Up


April 4, 2008 Girder Haul-In
Trucks took the same route again today. Five girders were delivered to the site by 8:45 a.m.
Last girder was placed into position on the bridge at approximately 12:05 p.m.
Click photos to view larger image size.

First girder makes it's way up into position
Last girder for this span is placed into position


April 7, 2008 Girder Haul-In
Trucks arrived a bit later today due to a delay at the Hood Canal Bridge.
Last girder was placed into position on the bridge at approximately 2:30 p.m.
Click photos to view larger image size.

Trucks arrive at site
Girder is lifted up
Girder lifted into position
Third girder is lowered into position


April 9, 2008 Girder Haul-In
The last five girders arrived and were in place by approximately 12:30 p.m.
Tumwater Truck Route SR117 reopened at 12:58 p.m.
Thank you for your patience during this major milestone in the project
Click photos to view larger image size.

Trucks arrive at site
Girder is lifted up
Girder lifted into position
Third girder is lowered into position

April 9, 2008 at 12:58 p.m.
TUMWATER TRUCK ROUTE SR117 REOPENS TO ALL THROUGH TRAFFIC

Thank you for your cooperation and patience!


Look up.....look way up.April 9, 2008 The last 5 of the 25 girders for the Tumwater Creek Bridge were delivered and set into place on Wednesday, April 9. Trucks arrived at approximately 7:00 a.m. and entered Front Street, travel west onto Marine Drive and then turned south onto the Tumwater Truck Route SR 117, then continued west onto US Highway 101.

Click photo to view larger image size.

Trucks turned right at Laird's Corner then headed north onto Laird Road and then east onto Edgewood Drive and Lauridsen Boulevard. Trucks then turned north onto "C" Street, then west on 8th Street to prepare to back up to the construction area at "A" Street.

Trucks make very wide, precise and slow turns. Trucks were escorted through the city by the Port Angeles Police Department. The Police Department will provide traffic control until those responsibilities were transferred to Parson's Construction for the final maneuvering of the trucks.

The City realizes that travel has been and will continue to be greatly affected during the replacement of the 8th Street Bridges. Please consider alternate routes and allowing extra time to travel.

Safety of the public, pedestrians and motorists is a top priority and traffic will continue to be monitored during the project. Please drive courteously and obey all traffic signs and especially posted speed limits.

Detour routes, traffic revisions and the anticipated construction schedule are posted as soon as they are available.

 

 

The first two trucks back into position

The girders were manufactured by Concrete Technology Corporation and will be transported from Tacoma with special heavy-capacity trucks via Van Dyke, Inc.

Transportation of the girders required coordination with several agencies along the route and special permitting by the Washington State Department of Transportation.

Detour routes, traffic revisions, anticipated construction schedule and project updates will be posted as soon as they become available. Questions and comments can be directed to Teresa Pierce, Executive Communications Coordinator at 360-417-4630 or .


Project Engineer, Jim MahlumProject Trivia
Each of the new 8th Street Bridges will have 8 shaft casings. Each shaft casing requires approximately 100 yards of concrete.

On the right: Project Manager, Jim Mahlum stands inside one of the rebar units that will be placed inside of the shaft casings. Each will hold 100 yards of concrete. Click photo to view larger images size.

Questions and comments can be directed to Jim Mahlum, Project Manager at 360-417-4701 or by email at: or Teresa Pierce, Executive Communications Coordinator at 360-417-4630 or .


Questions and Comments
Questions and comments can be directed to Jim Mahlum, Project Manager at 360-417-4701 or by email at: or Teresa Pierce, Executive Communications Coordinator at 360-417-4630 or .


Demolition and Construction Ceremony - August 28
To celebrate the beginning of this $18.4 million dollar project that will replace both 8th Street Bridges, a special ceremony was held on Tuesday, August 28th on the west side of the Tumwater Creek Bridge at the 8th & "A" Street intersection.

Bridge Demo Ceremony participants Over she goes!
Click photos to view larger image sizes

In addition to celebrating the building of the new bridges, the ceremony reflected on the history of the old bridges as they are two of the largest and longest wooden structure bridges remaining in Washington State.

City of Port Angeles Mayor Karen Rogers, City Councilmembers, City Manager Madsen, City Department Heads and Staff joined representatives of Parsons Construction, Exeltech Consulting, and the Washington State Department of Transportation for this brief ceremony.

~ In Partnership With the Community ~


A Little Bridge History
Old BridgeThe current bridges are not the first ones to span both Valley Creek and Tumwater Creek. In 1913 bridges were built but started to deteriorate in 1928 due to the heavier loads caused by increased use of the new method of transportation called the "automobile". The State was asked to make evaluations and multiple delays occurred due to funding and design changes.

Finally the current bridges were built in 1936 and were constructed with 800,000 board feet of prefabricated creosoted Douglas Fir. At the time, it was expected that the timbers would resist decay and termites for about 40 years.

These bridges were designed by the Washington Emergency Relief Administration and the Public Works Administration and were built at a cost of $67,000 each. The bridges were actually designed twice. It was originally hoped to build the bridges out of concrete, however wood timber construction was much less expensive and became the chosen material. Contrast that with the new bridges being built today where steel was the first choice and concrete was now the least expensive material.

In 1938, citizens petitioned City Council to install sidewalks and fencing for child safety. Those sidewalks and fencing have remained in place and are what you can see today as the bridges are demolished.

A section of the fencing and two bollards have been donated to the Clallam County Historical Society.


BID AWARDED ON 8th STREET BRIDGES PROJECT - April 4, 2007
View from under one of the bridgesCity Council has awarded the base bid on the 8th Street Bridges Replacement Project to Parsons RCI, Inc. of Sumner Washington, in the amount of $18,416,067.20. Five bids were opened on March 13th, 2007 with Parsons submitting the low responsible bid.

The base bid consists of the removal of the existing timber bridges and replacement with 758 foot long reinforced concrete structures.

Concrete bridgeThe bridges will be 34 feet wide, curb to curb (12 foot lanes and 5 foot bike shoulders) with 6.5 foot wide sidewalks on each side.

The base bid includes standard WSDOT railing and lighting and extensive stormwater systems for stream protection, wetland restoration, permanent traffic and temporary detour signals, and related utility relocations.


DRAWINGS
Artist drawings, or renderings, of the bridges are available below. Please click any photo to view in a larger image size.

Bridge Overview
Barrier included with base bid


Questions or Comments?
Please direct your questions or comments to:

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.


~ CONTACT INFO ~

Jim Mahlum

Project Engineer

360-417-4701
or
360-417-4800

Email:
bridges@cityofpa.us
or
jmahlum@cityofpa.us

_______

Teresa Pierce
Executive
Communications
Coordinator

360-417-4630
or
tpierce@cityofpa.us